Requirements
- New equipment for upgrades must hold the following HSPF2/HSPF efficiencies (cooling capacity; BTU/H):
- <65,000 Split-System, 8.1 HSPF2 or 9.6 HSPF
- <65,000 Single Package: 7.0 HSPF2 or 8.3 HSPF
- >65,000 and <135,000: 3.5 COP
- >135,000 and <240,000: 3.4 COP
- >240,000: 3.4 COP
- AHRI Certificate
- Projects must be installed by a licensed and bonded contractor
- Equipment or contractor invoice showing equipment order or purchase date, along with the installed cost
- Completed Commercial Air-Source Heat Pump Information Form (PDF)
- Post-inspection